The certification process requires a plan of subdivision prepared by a licensed land surveyor to be lodged with Council through SPEAR, with a Form 1 certification application under the Subdivision Act 1988.
The plan shows the proposed lots, size, area and any easements required.
The certification application is referred by Council to any relevant referral and servicing authorities (which may include VicRoads, Gippsland Water, West Gippsland Catchment Management Authority AusNet Electricity Services, AusNet Transmission Group, APA Group, Country Fire Authority, Fire Rescue Victoria and Department of Environment, Land, Water and Planning).
These authorities have 28 days in which to respond to the referral with any conditions they may to choose to place on the application.
Your plans cannot be certified by Council until a planning permit has been issued for the subdivision and pre-certification requirements are met, such as registration of a Section 173 Agreement.
However, the two processes can run concurrently.